EDIA

(June 2012)

The Office of Project Assessment conducted a survey of project EDIA cost data. Below is the summary of the survey results (May 2012) of project EDIA cost as a percent of construction cost (R&D and Commissioning and Testing have been taken out of the construction cost). Those who are interested in obtaining more detail information of the survey results or the basis for the summary charts, please contact Kin Chao (301) 903-4116;
[email protected].