Determination Date Name of Action: Description Categorical Exclusion Number
1/6/2025 Kirk Road Sanitary Sewer Improvements CX B1.31, B5.4
11/26/2024 Kautz Road Construction Entrance CX
10/22/2024 Improved Pavement Processes Using Compact SRF Electron Accelerators CX B3.6, B3.10
10/8/2024 Emergency Response and Transformer Repair at Kautz Road Substation CX B4.6, B4.11, B5.6, B6.1
6/11/2024 Utilities Infrastructure Project B1.15, B1.16, B1.18, B1.23, B1.34, B1.3, B2.1, B2.5, B4.11, B5.2
3/22/2024 DWS Loop Feed at GCC B5.5
1/29/2024 Electric Vehicle Charging Station Installations B5.23
6/2/2022 NEPA EENF for Mahoney Creek Floodplain Construction B1.33, B2.5
6/2/2022 Mahoney Creek Stormwater Detention Basin CX B1.33, B2.5
3/23/2022 National Environmental Policy Act Determination at Fermi National Accelerator Laboratory – Nevis Blocks Removal B1.10; B1.30